Home/Case Studies/Fujian Sangang Steelmaking Plant — EPC Wash Station for No. 1 & No. 2 Converter Slag Yards
Fujian Sangang Steelmaking Plant — EPC Wash Station for No. 1 & No. 2 Converter Slag Yards
Steel & Metallurgy

Fujian Sangang Steelmaking Plant — EPC Wash Station for No. 1 & No. 2 Converter Slag Yards

On-site · slag-yard wash station
甲方:福建三钢闽光股份有限公司炼钢厂 · 乙方:上海臻欧实业发展有限公司(凯美龙)
← ← Back to all cases

Overview

One automatic wash station was added on the eastern road of the No. 1 steelmaking slag yard and another on the western road of the No. 2 yard, delivered as a turnkey EPC package: design, fabrication, supply, installation, commissioning, acceptance, training and after-sales service.

Client Profile

The steelmaking plant of Fujian Sangang Minguang added one automatic wash station on the eastern road of the No. 1 steelmaking slag yard and one on the western road of the No. 2 yard, to wash transport vehicles entering and leaving the workshop area. The No. 1 unit sits on the eastern slag-yard passage (bay H-J, between columns 16 and 18); the No. 2 unit sits on the western passage (west of row K, between columns 7 and 9). The works are executed as a turnkey EPC package, with design and construction required to guarantee completeness, safety, environmental performance, rationality, and technical advancement and reliability.

The Challenge

  • Vehicles to be washed carry ore, scrap and steel slag; they are tractor units and heavy trucks with a gross weight of about 120 t.
  • Maximum vehicle dimensions are about 12 m long, 3.2 m wide and 4.5 m high; the plant road has a 4.5 m height limit.
  • Throughput targets: ≥100 vehicles/day at No. 1 steelmaking and ≥150 vehicles/day at No. 2; the wash station must carry a vehicle weight of ≥120 t.
  • The site adjoins live production areas, so safety protection and isolation measures are required during construction, and the existing plant drainage must not be damaged.
  • The works must comply with Fujian Sangang enterprise standard [2017] No. 118 “On-site 5S Management Standard”; safety and environmental facilities must follow the “three simultaneities” principle and AQ2001-2018 / AQ7011-2018.
  • Duration: delivery for use within six months of contract signature.

The Solution

Washing and recovery form one closed loop: both stations use modular zoning with the wash zone in series with an air-dry/drain zone, and wash water is recovered and recirculated through a settling system. A single EPC contract covers civil works, equipment, electrical and instrumentation. 现场组装 · 冲洗管路与喷嘴 | On site · wash piping and nozzles Turnkey EPC delivery — The EPC scope covers design, fabrication, supply, installation, commissioning, acceptance, training and after-sales service for both wash stations. The scope-split table assigns the station body, trench covers, installation fittings, foundations and the high-pressure wash system (nozzles, pumps, filtration, trench washing) to the contractor. High-pressure wash system — Each station has its own high-pressure wash system: 2 sets each of nozzles, pumps, filtration units and trench-washing units. Utilities and network interfaces — Power is tapped at the No. 1 steelmaking No. 2 furnace electrical room and the No. 2 converter electrical room; water at the DN200 industrial clean-water main and the DN200 medium-pressure process water main; the industrial control network connects at the respective engineer stations. Construction and safety — The contractor handles temporary removal, relocation and reinstatement of equipment and obstructions; non-metallic waste is treated safely and demolished metal components are sorted and transported to the designated location. A video monitoring system is provided throughout construction and recovered on completion.

Project Details

  • 设备安装实拍 · 泵组与管廊 | Installation · pump set and pipe rack
  • The two stations cover the No. 1 and No. 2 steelmaking slag yards respectively, meeting throughput requirements of ≥100 and ≥150 vehicles per day.
  • With a carrying capacity of ≥120 t, the stations handle heavy tractor units and trucks hauling ore, scrap and steel slag.
  • Turnkey EPC delivery places design, fabrication, supply, installation, commissioning, acceptance, training and after-sales with a single party — a clear responsibility interface and a controllable six-month schedule.
  • Construction complies with 5S management and the “three simultaneities” safety and environmental requirements, without damaging the existing plant drainage.
  • A full-time video monitoring system during construction, recovered on completion, balances site safety with production order.

Building a wash station inside a live steel plant is usually less about the equipment and more about organising construction without stopping production. Bundling design, civil works, equipment and electrical into one EPC contract gives a clear responsibility interface — the key to on-time delivery in projects like this.